Methodology Note: This timeline documents events with source citations. Where dates are uncertain, this is noted. Where BHCR's self-reported dates cannot be independently confirmed, this is stated. (methodology)

Timeline of Events

  1. ITESM Monterrey Safety Study Completed

    Panama Green Innovations S.A. commissions a safety risk study on the HCR 410 refrigerant formula at the Tecnologico de Monterrey. The study notes that HC refrigerants are highly flammable (A3 equivalent) but can be used with proper handling. This is the earliest documented activity of the corporate cluster.

    Source Document(s):
  2. Eco Kold Version 1.0 Launched

    According to BHCR's corporate narrative, Version 1.0 of the Eco Kold refrigerant went to market and distributor partnerships began.

  3. UTP Efficiency Study Published

    The Universidad Tecnologica de Panama publishes a study showing a 36% efficiency gain for HCR 410 compared to R-410. An Eco Kold representative was present during the testing. This single study forms the foundation of all BHCR marketing efficiency claims to date.

    Source Document(s):
  4. Claimed Installation: Immigration Office

    BHCR claims 27 A/C units were converted to HCR 410, purportedly resulting in a 47% electric bill decrease. This claim is self-reported with no independent verification provided.

    Source Document(s):
  5. BHCR Claims EPA SNAP Submission

    BHCR marketing materials state an application was submitted to the EPA Stratospheric Protection Division for SNAP approval. Despite being submitted in 2022, no Federal Register notice exists confirming approval of HCR 410 as a drop-in replacement.

    Source Document(s):
  6. Core Laboratories Panama Analysis

    A molecular composition analysis is performed, identifying the substance as a hydrocarbon zeotropic mixture of 100% mineral origin.

    Source Document(s):
  7. UK Certifications Issues CE-4082

    UK Certifications issues a certificate claiming Ecodesign Directive compliance. Independent searches show this issuing body is not listed in the UKAS directory, casting doubt on the certification's legitimacy.

    Source Document(s):
  8. Oca Loca Commercial Installation

    BHCR converts a poorly-maintained 10-ton Daikin unit in Panama from R-410A to HCR 410. They log a 38% amperage reduction, though standard HVAC guidelines state that simply cleaning a dirty coil can achieve similar efficiency gains.

    Source Document(s):
  9. Real-World Testing Fails in Israel

    After importing the product following BHCR's guarantees, Konstantin Rize conducts 6 months of testing on standard Israeli cooling systems. The tests fail entirely, not meeting any of the manufacturer's efficiency or functionality promises. BHCR breaks its promise to send a representative and refuses a fair financial settlement.